What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 23 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Tye Lane | £31.70 |
| 2 | EDFE Aggregate S Eng 02 | £30.42 |
| 3 | Zenobe Capenhurst #4 | £29.92 |
| 4 | ClayTye Farm 1 | £27.48 |
| 5 | Contego | £27.36 |
| 6 | Ilmer Lane | £26.55 |
| 7 | Farnham | £26.37 |
| Region | £/MWh |
|---|---|
| Eastern | £31.3 |
| Merseyside and North Wales | £29.9 |
| Southern | £26.4 |
| South Western | £22.8 |
| South Wales | £22.0 |
| South Eastern | £20.7 |
| Yorkshire | £15.9 |