What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 93 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Shoreham | £11.56 |
| 2 | GridBeyond L0EN | £11.00 |
| 3 | West Burton B 1 | £10.99 |
| 4 | Tebworth Park | £8.08 |
| 5 | F & S Energy #02 | £8.06 |
| 6 | F & S Energy #03 | £8.05 |
| 7 | Carrington Ltd - 2 | £8.05 |
| Region | £/MWh |
|---|---|
| North Western | £6.3 |
| Eastern | £6.3 |
| Midlands | £2.2 |
| Northern | £2.2 |