# | Unit | £/MWh |
|---|---|---|
| 1 | Capenhurst | £74.19 |
| 2 | SUNDON | £74.07 |
| 3 | BREDBURY | £73.86 |
| 4 | Bulphan Fen | £72.56 |
| 5 | EDFE Aggregate S Eng 02 | £72.10 |
| 6 | Pivot Coventry | £71.91 |
| 7 | EDF Aggregated Unit 05 | £71.18 |
| Region | £/MWh |
|---|---|
| Merseyside and North Wales | £74.2 |
| Midlands | £71.9 |
| North Western | £65.8 |
| South Wales | £65.3 |
| Eastern | £64.0 |
| Northern | £63.4 |
| Yorkshire | £59.8 |
| East Midlands | £59.0 |
| Southern | £53.2 |
| South Eastern | £52.6 |