What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 37 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Ferrybridge-1 | £7.74 |
| 2 | Jamesfield 2 | £6.50 |
| 3 | Jamesfield 1 | £6.47 |
| 4 | Keadby-2 Main | £5.74 |
| 5 | Kilmarnock South | £5.64 |
| 6 | Capenhurst | £5.63 |
| 7 | Kilmarnock South | £5.37 |
| Region | £/MWh |
|---|---|
| North Scotland | £5.9 |
| Merseyside and North Wales | £5.6 |
| South Scotland | £5.4 |
| Eastern | £5.3 |
| Southern | £5.0 |
| South Eastern | £4.6 |
| South Western | £4.4 |
| Midlands | £4.0 |