What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 45 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | UK Power Reserve #08 | £19.18 |
| 2 | F & S Energy #02 | £12.89 |
| 3 | UKPR S East | £12.45 |
| 4 | Whitebirk | £11.68 |
| 5 | Oldham | £11.68 |
| 6 | Thame Road | £11.60 |
| 7 | Contego | £11.47 |
| Region | £/MWh |
|---|---|
| South Wales | £11.1 |
| North Western | £11.1 |
| South Eastern | £9.4 |
| Yorkshire | £9.1 |
| Midlands | £8.6 |
| Northern | £8.6 |
| Southern | £8.5 |
| Eastern | £8.5 |
| South Western | £7.1 |