What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 36 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Bulphan Fen | £17.12 |
| 2 | SUNDON | £16.56 |
| 3 | EDF Aggregated Unit 05 | £16.07 |
| 4 | Burwell 1 | £16.00 |
| 5 | Newton wood | £16.00 |
| 6 | Pivot Coventry | £15.88 |
| 7 | Pivot Bustleholme | £15.70 |
| Region | £/MWh |
|---|---|
| East Midlands | £16.0 |
| Eastern | £15.8 |
| South Eastern | £14.8 |
| Yorkshire | £14.8 |
| North Western | £14.7 |
| Midlands | £14.5 |
| Southern | £14.5 |
| South Wales | £14.2 |
| Merseyside and North Wales | £14.1 |