What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 49 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | F & S Energy #02 | £25.68 |
| 2 | Tebworth Park | £25.50 |
| 3 | Sizing John | £25.41 |
| 4 | Staythorpe 1 | £24.50 |
| 5 | Staythorpe 2 | £24.50 |
| 6 | Shoreham | £24.25 |
| 7 | Carnegie Road 1 | £24.20 |
| Region | £/MWh |
|---|---|
| Merseyside and North Wales | £24.2 |
| Eastern | £23.6 |
| Yorkshire | £23.6 |
| South Eastern | £23.4 |
| North Western | £23.4 |
| Northern | £23.2 |
| South Scotland | £23.2 |
| South Western | £23.0 |
| Southern | £22.7 |
| Midlands | £22.7 |