What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 46 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Keadby-2 Main | £30.00 |
| 2 | Brigg | £28.92 |
| 3 | West Burton B 2 | £28.32 |
| 4 | Cottam Development Centre | £26.57 |
| 5 | Grain | £26.45 |
| 6 | Grain | £26.45 |
| 7 | Enfield Centre Ltd BMU1 | £25.88 |
| Region | £/MWh |
|---|---|
| North Western | £22.9 |
| Yorkshire | £22.7 |
| Eastern | £22.7 |
| Midlands | £22.3 |
| South Western | £21.3 |
| South Eastern | £21.1 |
| Southern | £18.3 |