What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 28 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | GridBeyond L0DN | £20.90 |
| 2 | Roaring Hill | £19.60 |
| 3 | Skelmersdale | £17.70 |
| 4 | Unit 3 | £16.91 |
| 5 | Sizing John | £16.72 |
| 6 | Kilmarnock South | £16.59 |
| 7 | Kilmarnock South | £16.59 |
| Region | £/MWh |
|---|---|
| Eastern | £16.2 |
| South Scotland | £16.2 |
| Yorkshire | £16.1 |
| North Western | £15.2 |
| South Western | £14.3 |
| South Eastern | £14.0 |
| Southern | £13.9 |
| Midlands | £12.9 |
| Northern | £11.2 |