What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 23 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Shoreham | £23.00 |
| 2 | Didcot B main 5 | £20.57 |
| 3 | Seabank Module 2 | £20.00 |
| 4 | Unit 1 | £19.37 |
| 5 | GridBeyond L0DN | £16.42 |
| 6 | SOUTH HUMBER BANK P/S | £15.00 |
| 7 | Exergy Solutions E00E | £12.26 |
| Region | £/MWh |
|---|---|
| Eastern | £10.2 |
| Southern | £9.9 |
| North Western | £9.6 |
| South Eastern | £8.9 |
| South Western | £7.3 |
| Midlands | £7.0 |
| North Scotland | £6.5 |