What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 31 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | EDF Energy F01C | £20.87 |
| 2 | SUNDON | £19.98 |
| 3 | Zenobe Capenhurst #4 | £19.82 |
| 4 | Larks Green | £19.74 |
| 5 | EDFE Aggregate S Eng 02 | £19.66 |
| 6 | BESS Holdco 2 EN7H | £19.57 |
| 7 | Zenobe Capenhurst #2 | £19.21 |
| Region | £/MWh |
|---|---|
| South Western | £19.4 |
| Merseyside and North Wales | £19.4 |
| Southern | £17.2 |
| Midlands | £14.1 |
| Eastern | £13.6 |
| North Western | £11.2 |
| South Wales | £11.1 |
| Yorkshire | £10.4 |
| South Eastern | £9.7 |
| East Midlands | £9.5 |
| Northern | £7.6 |