What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 13 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Chapel Farm | £0.50 |
| 2 | ClayTye Farm 2 | £0.46 |
| 3 | Jamesfield 1 | £0.42 |
| 4 | Roaring Hill | £0.41 |
| 5 | Immingham CHP | £0.40 |
| 6 | EDFE Aggregate N Scot 1 | £0.39 |
| 7 | Unit 1 | £0.37 |
| Region | £/MWh |
|---|---|
| North Scotland | £0.4 |
| South Scotland | £0.4 |
| Eastern | £0.4 |
| Yorkshire | £0.4 |
| South Wales | £0.3 |
| Southern | £0.3 |
| South Eastern | £0.3 |