What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 21 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Cottam Development Centre | £13.57 |
| 2 | Holes Bay | £8.80 |
| 3 | ECOTRICITY C05L | £8.50 |
| 4 | Ocker Hill | £7.43 |
| 5 | Burwell Weirs Drove | £7.20 |
| 6 | Port of Tyne | £7.20 |
| 7 | GridBeyond L02E | £7.14 |
| Region | £/MWh |
|---|---|
| Southern | £7.9 |
| Midlands | £7.4 |
| Northern | £7.2 |
| North Western | £6.9 |
| Eastern | £6.8 |