What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 40 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Didcot B main 5 | £16.00 |
| 2 | Keadby-2 Main | £16.00 |
| 3 | Cottam Development Centre | £15.02 |
| 4 | Carrington Ltd - 2 | £13.27 |
| 5 | Unit 3 | £13.27 |
| 6 | Rocksavage | £13.27 |
| 7 | Carrington Ltd - 1 | £13.20 |
| Region | £/MWh |
|---|---|
| Midlands | £11.8 |
| South Western | £11.5 |
| Yorkshire | £11.4 |
| South Wales | £11.0 |
| Northern | £11.0 |
| Eastern | £10.1 |
| Southern | £9.3 |
| South Eastern | £8.1 |
| North Western | £6.9 |