What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 19 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Didcot B main 5 | £50.00 |
| 2 | KGL 1 | £49.60 |
| 3 | Marchwood | £48.00 |
| 4 | Seabank Module 2 | £46.00 |
| 5 | Unit 2 | £45.23 |
| 6 | Unit 3 | £44.76 |
| 7 | Tye Lane | £44.45 |
| Region | £/MWh |
|---|---|
| Midlands | £39.6 |
| Southern | £39.6 |
| Yorkshire | £37.3 |
| Northern | £36.3 |
| South Wales | £35.4 |
| South Western | £32.9 |
| South Eastern | £32.8 |
| Eastern | £32.8 |