What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 30 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Unit 3 | £10.61 |
| 2 | Carrington Ltd - 2 | £8.40 |
| 3 | Native River | £6.10 |
| 4 | Tebworth Park | £5.96 |
| 5 | Grain | £5.61 |
| 6 | Kings Lynn A | £5.13 |
| 7 | West Burton B 3 | £4.63 |
| Region | £/MWh |
|---|---|
| South Western | £6.1 |
| Eastern | £4.1 |
| South Scotland | £4.0 |
| Yorkshire | £3.9 |
| South Eastern | £2.3 |
| Southern | £1.8 |