# | Unit | £/MWh |
|---|---|---|
| 1 | Didcot B main 6 | £17.75 |
| 2 | Didcot B main 5 | £17.10 |
| 3 | Marchwood | £16.00 |
| 4 | Centrica Business Solutions S05L | £14.69 |
| 5 | Carrington Ltd - 2 | £14.58 |
| 6 | Unit 2 | £14.58 |
| 7 | SOUTH HUMBER BANK P/S | £12.87 |
| Region | £/MWh |
|---|---|
| North Western | £10.7 |
| Eastern | £10.4 |
| Yorkshire | £10.3 |
| Midlands | £9.9 |
| Southern | £9.7 |
| South Eastern | £9.6 |