What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 35 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Pembroke 21 | £24.88 |
| 2 | Pembroke 11 | £24.82 |
| 3 | Unit 2 | £22.40 |
| 4 | Unit 1 | £22.38 |
| 5 | SOUTH HUMBER BANK P/S | £21.13 |
| 6 | Didcot B main 6 | £19.69 |
| 7 | Wormald Green | £14.21 |
| Region | £/MWh |
|---|---|
| Northern | £14.2 |
| South Western | £10.6 |
| Yorkshire | £10.1 |
| North Western | £7.5 |
| Southern | £7.5 |
| Eastern | £7.1 |
| South Eastern | £6.4 |