What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 3 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Pembroke 11 | £76.38 |
| 2 | Keadby-2 Main | £51.82 |
| 3 | Wormald Green | £50.14 |
| 4 | KGL 1 | £45.36 |
| 5 | Unit 3 | £42.51 |
| 6 | SOUTH HUMBER BANK P/S | £38.89 |
| 7 | Bloxwich | £38.71 |
| Region | £/MWh |
|---|---|
| Northern | £50.1 |
| South Wales | £38.5 |
| Southern | £33.9 |
| North Western | £32.0 |
| South Eastern | £31.7 |
| Merseyside and North Wales | £31.1 |
| Eastern | £20.4 |
| Midlands | £20.3 |