What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 90 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Optimo Energy T01N | £89.50 |
| 2 | Seabank Module 2 | £71.44 |
| 3 | Staythorpe 1 | £66.10 |
| 4 | GridBeyond L0DN | £55.08 |
| 5 | GridBeyond L0EN | £55.08 |
| 6 | Grain | £51.60 |
| 7 | BMUid for Sutton Bridge | £50.02 |
| Region | £/MWh |
|---|---|
| South Eastern | £41.2 |
| North Scotland | £37.2 |
| Midlands | £33.7 |
| North Western | £28.5 |
| Eastern | £20.6 |
| Northern | £20.3 |
| South Scotland | £20.2 |
| Southern | £19.0 |
| Merseyside and North Wales | £17.8 |
| South Western | £17.5 |
| East Midlands | £16.5 |