What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 37 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Langage | £12.50 |
| 2 | Grain | £12.30 |
| 3 | Unit 1 | £10.29 |
| 4 | Tebworth Park | £9.31 |
| 5 | F & S Energy #03 | £9.04 |
| 6 | Wormald Green | £8.74 |
| 7 | Lakeside | £8.68 |
| Region | £/MWh |
|---|---|
| Northern | £8.7 |
| South Eastern | £8.6 |
| Yorkshire | £8.3 |
| South Wales | £7.2 |
| Eastern | £7.2 |
| North Western | £6.7 |
| South Western | £5.8 |
| Midlands | £5.7 |