What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 44 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | West Burton B 2 | £20.39 |
| 2 | Cowley | £18.63 |
| 3 | Shoreham | £18.45 |
| 4 | Lakeside | £18.25 |
| 5 | ZENOBE BLACKHILLOCK #4 | £18.06 |
| 6 | ZENOBE BLACKHILLOCK #1 | £18.05 |
| 7 | EDFE Aggregate S Eng 02 | £16.70 |
| Region | £/MWh |
|---|---|
| Yorkshire | £18.3 |
| North Scotland | £18.0 |
| Midlands | £15.2 |
| South Eastern | £15.0 |
| South Western | £13.7 |
| Merseyside and North Wales | £11.0 |
| North Western | £11.0 |
| Eastern | £10.6 |