What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 22 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Didcot B main 6 | £33.54 |
| 2 | Didcot B main 5 | £31.12 |
| 3 | Seabank Module 2 | £29.25 |
| 4 | Kings Lynn A | £27.50 |
| 5 | Unit 3 | £26.28 |
| 6 | GridBeyond L0DN | £25.68 |
| 7 | Carrington Ltd - 1 | £22.06 |
| Region | £/MWh |
|---|---|
| North Scotland | £20.0 |
| South Scotland | £18.3 |
| South Eastern | £15.4 |
| Eastern | £14.9 |
| North Western | £10.3 |
| South Wales | £10.0 |