What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 17 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Shoreham | £20.53 |
| 2 | Bulphan Fen | £15.25 |
| 3 | Zenobe Capenhurst #2 | £13.14 |
| 4 | Zenobe Capenhurst #3 | £13.14 |
| 5 | Zenobe Capenhurst #4 | £13.14 |
| 6 | Pivot Bustleholme | £12.27 |
| 7 | Zenobe Capenhurst #1 | £11.50 |
| Region | £/MWh |
|---|---|
| Merseyside and North Wales | £12.7 |
| Midlands | £12.3 |
| Eastern | £9.0 |
| South Eastern | £7.6 |
| Northern | £5.3 |
| South Western | £3.0 |