What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 7 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Immingham CHP | £75.70 |
| 2 | Keadby-2 Main | £68.84 |
| 3 | Grain | £59.87 |
| 4 | Grain | £59.87 |
| 5 | Sizing John | £53.90 |
| Region | £/MWh |
|---|---|
| Eastern | £53.9 |