What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 8 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | EDFE Aggregate N Scot 1 | £3.78 |
| 2 | Carnegie Road 1 | £3.47 |
| 3 | Thame Road | £3.04 |
| 4 | Sizing John | £2.64 |
| 5 | Statkraft Markets #09 | £2.33 |
| 6 | Native River | £2.17 |
| 7 | Centrica Business Solutions S05L | £2.00 |
| Region | £/MWh |
|---|---|
| Merseyside and North Wales | £3.5 |
| Eastern | £2.8 |
| South Western | £2.2 |