What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 1 accepted unit with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | EDFE Aggregate N Scot 1 | £228.22 |
| 2 | Peterhead Block 1 | £203.95 |
| 3 | EDFE Aggregate S Eng 02 | £172.45 |
| 4 | Rocksavage | £154.56 |
| 5 | Immingham CHP | £150.30 |
| 6 | Shoreham | £106.02 |
| 7 | Keadby-2 Main | £89.00 |
| Region | £/MWh |
|---|---|
| North Western | £89.0 |
| Yorkshire | £89.0 |