What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 26 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | EDFE Aggregate N Scot 1 | £4.80 |
| 2 | Marchwood | £4.42 |
| 3 | Little Raith | £3.90 |
| 4 | Spalding | £3.65 |
| 5 | Statkraft Markets #05 | £3.48 |
| 6 | Hawthorn Pit | £3.38 |
| 7 | Cottam Development Centre | £3.35 |
| Region | £/MWh |
|---|---|
| South Scotland | £3.9 |
| Northern | £3.4 |
| Eastern | £3.1 |