What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 32 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Thame Road | £572.80 |
| 2 | Staythorpe 1 | £533.63 |
| 3 | Damhead Creek | £533.61 |
| 4 | Staythorpe 2 | £533.61 |
| 5 | Immingham CHP | £533.50 |
| Region | £/MWh |
|---|---|
| Eastern | £572.8 |