What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 13 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Tebworth Park | £6.35 |
| 2 | F & S Energy #03 | £6.27 |
| 3 | Keadby-2 Main | £5.73 |
| 4 | Rocksavage | £4.94 |
| 5 | SOUTH HUMBER BANK P/S | £4.48 |
| 6 | SOUTH HUMBER BANK P/S | £3.63 |
| Region | £/MWh |
|---|---|
| Eastern | £6.4 |