What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 32 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | KGL 1 | £13.86 |
| 2 | SOUTH HUMBER BANK P/S | £12.93 |
| 3 | Medway | £11.88 |
| 4 | Flexitricity #03 | £9.20 |
| 5 | Flexitricity #03 | £9.20 |
| 6 | Carrington Ltd - 2 | £8.58 |
| 7 | Carrington Ltd - 1 | £8.27 |
| Region | £/MWh |
|---|---|
| South Eastern | £8.1 |
| Southern | £5.1 |