Little Barford main 1 (CCGT) — LBAR-1 | Skipedia
Technology & Units
/
Little Barford main 1
Little Barford main 1
CCGT · Eastern · LBAR-1
Total Skip Cost
£101K
Skip Cost Rate
£70.40/MWh
£/MWh skipped · all-time
National Rank
178th worst
of 465 units · all technologies
#178
/465
National
Region Rank
12th worst
of 36 in Eastern · all technologies
#12
/36
Region
Skip Costs
All-time total:
£101K
Showing data for All time
7d
Last 7 days
30d
Last 30 days
365d
Last 365 days
All
All time
£58.2K
£43.7K
£29.1K
£14.6K
£0
Mar
Jun
Jul
Aug
Oct
Nov
Dec
Jan
Feb
Mar
May
Eastern — CCGT — Skip Cost Ranking
Worst 40%
5 units
View all in Eastern
Eastern
National
CCGT
All technologies
Volume ranking
0%
25%
50%
Parity
75%
100%
Mar 25
Jun 25
Aug 25
Nov 25
Jan 26
May 26
Most skipped
Least skipped
Most skipped (top 25%)
Around parity
Least skipped (bottom 25%)
Unit ranking
1
Rye House
CCGT
£31.50/MWh
£33.0K
2
Little Barford main 1
CCGT
£14.78/MWh
£101K
3
Kings Lynn A
CCGT
£12.84/MWh
£119K
4
Great Yarmouth
CCGT
£6.57/MWh
£38.5K
5
Peterborough
CCGT
—
£1.3K