What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 49 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | GridBeyond L0EN | £43.35 |
| 2 | SOUTH HUMBER BANK P/S | £41.14 |
| 3 | Didcot B main 5 | £38.87 |
| 4 | GridBeyond L0DN | £25.26 |
| 5 | Spalding | £18.56 |
| 6 | West Burton B 3 | £18.50 |
| 7 | Lester Way | £18.49 |
| Region | £/MWh |
|---|---|
| East Midlands | £14.6 |