What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 27 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Marchwood | £62.00 |
| 2 | West Burton B 2 | £57.56 |
| 3 | West Burton B 3 | £57.56 |
| 4 | Exergy Solutions E00E | £56.50 |
| 5 | SOUTH HUMBER BANK P/S | £52.95 |
| 6 | Flexitricity #04 | £52.94 |
| 7 | SOUTH HUMBER BANK P/S | £43.71 |