What was actually dispatched vs the merit order above. Shows accepted, skipped, and out-of-merit (favoured) units.
Excludes 20 accepted units with <1 MWh volume
Units with MZT/MNZT/NDZ ≥31 minutes (and not running) and volumes outside SEL-MEL/SIL-MIL ranges. What remains are unexplained skips.
# | Unit | £/MWh |
|---|---|---|
| 1 | Unit 1 | £34.86 |
| 2 | Keadby-2 Main | £28.61 |
| 3 | KGL 1 | £24.89 |
| 4 | SOUTH HUMBER BANK P/S | £23.32 |
| 5 | Flexitricity #03 | £16.97 |
| 6 | Carrington Ltd - 2 | £15.90 |
| 7 | Carrington Ltd - 1 | £15.38 |
| Region | £/MWh |
|---|---|
| Northern | £11.2 |
| South Wales | £10.3 |
| South Eastern | £9.0 |
| North Western | £7.2 |